What Part L asks of a rooflight
Part L of the Building Regulations sets the minimum thermal standard for any rooflight you add or replace in England, and for most domestic work the headline figure is a limiting U-value of 2.2 W/m²K, measured with the unit lying flat.
Part L is the conservation of fuel and power section of the Building Regulations. Its guidance lives in Approved Document L, and the edition that matters for homes today is Volume 1, 2021 edition, which came into force in June 2022. That document replaced the older approach, where every type of glazing was judged in much the same way, with a set of tables that treat windows, roof windows, rooflights and doors as separate elements, each with its own limit.
For a rooflight, the rules come down to three questions. Does the whole unit, frame and glass together, reach the limiting value? Has that value been worked out in the correct position? And, if the rooflight is part of a larger project such as an extension or a new home, does it fit inside the overall energy calculation for that project? Each question has its own answer, and each one catches out a different kind of job.
It helps to be clear about what Part L does not do. It is not a planning rule: it says nothing about how a skylight looks from the street, and it applies whether or not planning permission is needed. It is not a daylight standard either. A rooflight can pass Part L comfortably and still light the wrong end of a kitchen or overheat a loft bedroom in July. Part L is a floor for heat loss. The rest of the specification, including where the light lands and how much sun comes through, is a design decision that sits on top of it.
This guide covers England. Wales has its own Part L with different figures, and Scotland works to a separate set of technical standards, so a datasheet written for one nation does not automatically prove compliance in another. For the physics behind the numbers, our guide to rooflight U-values explained goes into how the figure is measured; this page is about what the regulations do with it.
The 2.2 W/m²K limiting value, and why it is measured lying flat
The limiting U-value is the worst performance the regulations will accept for a single new or replacement rooflight, and under the 2021 edition it has to be quoted for the unit in the horizontal plane rather than standing upright like a wall window.
A limiting value is a backstop. It stops a poor element being installed even where the rest of a building is good enough to hide it in a calculation. For rooflights in homes, Approved Document L sets that backstop at 2.2 W/m²K, and a footnote to the tables makes clear that the figure applies to the rooflight assessed in the horizontal position. That footnote is the part that changed the market.
Glazing has traditionally been tested and quoted as if it stood vertically, because that is how windows are made and sold. A sealed unit behaves differently when it lies flat. The warm inner pane sits underneath the cold outer pane, so the gas in the cavity circulates freely: warm gas rises from the inner pane, cools against the outer one and falls back. That convection carries more heat across the cavity than it would in a vertical unit, where the gas moves in a slower loop. The same sealed unit therefore has a worse U-value lying flat than standing up, and the gap can be several tenths of a W/m²K depending on the cavity width and gas fill.
Before the 2021 edition, a manufacturer could quote the vertical figure for a flat rooflight and it would look better than the unit would ever perform on a roof. Now the horizontal figure is the one that counts. When you compare products, check which angle the U-value refers to. A datasheet that quotes 1.4 W/m²K without saying whether that is vertical, horizontal or a centre-pane value is not telling you enough to judge compliance.
The value is also a whole-unit figure. A glass-only number, sometimes called the centre-pane or Ug value, leaves out the frame and the spacer bar around the edge of the sealed unit, which are the coldest parts of most rooflights. A good sealed unit in a frame with no thermal break can post an attractive Ug and still miss 2.2 W/m²K once the frame is included. The frame question is covered in more detail in our guide to thermally broken rooflight frames.

The notional dwelling and its 1.7 W/m²K rooflight
New homes are not judged element by element alone: they are compared against a notional dwelling, an imaginary version of the same house built to a fixed specification, and in that reference house the rooflights are assumed to reach 1.7 W/m²K.
When a new house or flat is designed, an energy assessor models it using the Standard Assessment Procedure. The software builds a second, notional version of the same home, with the same shape, floor area and orientation, but with every element set to a reference specification. The notional dwelling is where the targets come from: the target emission rate, the target primary energy rate and the target fabric energy efficiency. The real design has to perform at least as well as the notional one on each of those measures.
In the notional dwelling, rooflights are given a U-value of 1.7 W/m²K. That is well below the 2.2 limiting value, and it matters because of how the comparison works. If the real design uses rooflights at exactly 2.2, it is losing more heat through the roof glazing than the notional house, and that shortfall has to be made up elsewhere: better walls, better windows, a more efficient heating system. If the real rooflights match or beat 1.7, they stop being a drag on the calculation.
So the 2.2 figure tells you what is legal for a single element, and the 1.7 figure tells you what the new-build target assumes. The two numbers are sometimes confused in product literature, where a unit that meets 2.2 is described as meeting Part L without saying which part of Part L. For a new home, meeting the limiting value is the start of the conversation, not the end.
There is a practical reason this matters beyond the paperwork. The notional specification is also a sensible comfort target. A rooflight at around 1.7 W/m²K or better keeps the inner glass warm enough that the cold downdraught people feel under older units is much reduced, and the risk of condensation on the inner pane drops with it. We look at that effect in rooflight condensation.
New rooflights in existing homes and extensions
Adding a rooflight to an existing Cambridge home, or building an extension with one, brings the work under Part L, and the new unit has to meet the 2.2 W/m²K limiting value in its own right.
Cutting a new opening in an existing roof and fitting a rooflight is building work under the Regulations. The roof around the opening is being altered, the rooflight is a new element of the thermal envelope, and Building Control will expect to see a unit that reaches the limiting value. Because the work also touches the structure of the roof, Part A (structure) usually applies alongside Part L, with Part B (fire) and Part K (protection from falling and safety glazing) in play depending on where the rooflight goes.
Extensions add one more layer. Approved Document L limits the combined area of windows, roof windows, rooflights and doors in an extension to 25 per cent of the extension's floor area, plus the area of any existing windows or doors that the extension covers up. A rear kitchen extension on a Romsey or Petersfield terrace, with sliding doors across the back and a large rooflight over the island, can exceed that allowance quickly. When it does, the design has to show compliance another way, by an area-weighted calculation or a SAP comparison showing the extension performs no worse than one that kept to the 25 per cent limit with elements at the limiting values.
In practice, that means the rooflight specification and the rest of the glazing are linked. A better rooflight, closer to the notional 1.7 W/m²K or lower, can give an architect or assessor room to keep the glazed doors the client wants. A rooflight that only just scrapes 2.2 can force compromises elsewhere. Working out the size and position of the glass before the drawings are fixed is part of how we plan the light, and it saves redrawing an extension when the numbers come back.
Loft conversions follow the same principle. Rooflights and roof windows in a new loft room are new elements, and the U-value of the glazing sits within the Building Control application for the conversion as a whole, along with the insulation of the new rafters, the stair, fire escape and ventilation.
Replacing an existing rooflight
Swapping an old rooflight for a new one is treated as replacing a controlled fitting, so the new unit must meet the same 2.2 W/m²K limiting value and the work has to be notified to Building Control.
Replacement is where the requirement surprises people. The logic is that if you are renewing an element of the building's thermal envelope, the new one should meet the current standard rather than the standard the old one was built to. A single-glazed wired-glass rooflight from the 1970s, a polycarbonate dome over a landing, or a misted double-glazed unit from the 1990s are all well short of today's figure, and a like-for-like replacement in the old specification is not an option.
The notification can be handled in two ways: by an installer registered with a self-certification scheme covering that type of work, or by a building notice or full plans application to the local authority's building control service. Either route ends with a record that the work complies, which you will want when you sell the house. On our own jobs, we handle the Building Control notification where the work is notifiable, so you do not have to arrange it separately.
There is a narrow allowance for cases where full compliance is not technically or functionally feasible, and some flexibility for historic buildings, which we come to below. For an ordinary replacement in a sound opening, those exceptions do not apply, and modern sealed units reach 2.2 W/m²K lying flat without difficulty. The shorter version of this question, with a direct answer, is in does a replacement rooflight have to meet Part L?, and the wider case for upgrading old glass is in upgrading single-glazed rooflights.
One knock-on to plan for: a new unit is usually thicker and heavier than the one it replaces. Moving from single glazing to a sealed double or triple unit can mean a new upstand or kerb on a flat roof, and a check that the opening and any timber trimmers can carry the extra weight. That is part of the replacement, not an extra, and it is why a replacement is specified from a survey of the actual opening.
Where each figure applies
The table below sets out which number governs which kind of job, so you can see at a glance whether 2.2 or 1.7 W/m²K is the figure your project is judged against.
| Project | Figure that governs | How it is checked |
|---|---|---|
| New rooflight in an existing roof | 2.2 W/m²K, horizontal | Building Control |
| Replacement rooflight | 2.2 W/m²K, horizontal | Notified as a controlled fitting |
| Extension within the 25% glazing allowance | 2.2 W/m²K, horizontal | Building Control |
| Extension over the allowance | Better than 2.2 to offset the extra glass | Area-weighted or SAP comparison |
| New home | 1.7 W/m²K in the notional dwelling | SAP against the targets |
The table is a guide to the principle, not a substitute for the Approved Document or for the view of the building control body on a particular project. Edge cases exist, such as a change of use that creates a new dwelling from a barn or a commercial building, where the new-build targets can apply to a building that already stands.
- Is the roof structure altered? For example rafters or joists cut and trimmed to make a new or bigger opening.
- Yes: usually a Building Regulations application to Building Control (the council or a registered building control approver) before work starts.
- No, for example a like-for-like replacement: usually self-certified by an installer in a competent person scheme, or notified to Building Control.
- Is it a listed building or in a conservation area, or a flat? These can change what is allowed.
- Yes: check with the council first. Listed building consent or planning permission may be needed.
- No: rooflights on a house are usually permitted development if they stand no more than 150mm proud of the roof slope, sit no higher than the ridge, and any on a side slope are obscure-glazed and fixed below 1.7m. Lanterns often stand higher, so check.
- Both answered: the work goes ahead. Keep the certificates, since a buyer’s solicitor will ask for them.
The diagram shows when rooflight work is notifiable and the two ways the notification can be made. Whichever route is used, the evidence Building Control needs is the same: the whole-unit U-value in the horizontal position, from the manufacturer's data for the exact size and glass being installed.
Reading a datasheet for compliance
A compliant rooflight is proved on paper before it is proved on the roof, and the checks are short once you know which lines of a datasheet to read.
When we specify a rooflight or skylight, these are the points we confirm before anything is ordered:
- The U-value is a whole-unit figure, frame included, not a centre-pane Ug.
- It is stated for the horizontal position, or for the actual pitch of a roof window.
- It relates to the size being fitted, since small units carry proportionally more frame and usually post a worse figure than the headline size in a brochure.
- It relates to the glass being fitted. Swapping to a different solar control coating or a laminated inner pane can change the U-value, so the figure has to match the final glass build-up.
- The upstand or kerb is insulated so that the rooflight is not sitting on a cold frame of timber that undoes the good glass.
The size point is worth dwelling on. A rooflight manufacturer may publish a U-value for one reference size, and a unit half that area can perform noticeably worse because the frame and edge make up a larger share of it. For a small rooflight over a landing or a shower room, it is worth asking for the figure at the real size.
The glass point links Part L to the light. The coatings and gas fills that bring a U-value down, described in low-E coatings and argon fill, also shift how much light and solar heat come through. Choosing between a double and triple unit changes the figure too, and the trade-offs of weight and light are set out in double vs triple glazed rooflights. The Part L check is one line; the choice behind it affects the room every day.
What Part L leaves to the designer
Part L controls how much heat a rooflight lets out in winter, but it does not set a limit on how much sun it lets in during summer, and that gap is where the light plan does most of its work.
A skylight that meets 2.2 W/m²K can still turn a room into a greenhouse. On the flat land around Cambridge, with open sky in every direction and no hills to cut off the afternoon sun, a large area of clear glass on a south or west slope gathers a lot of heat from May to September. The U-value says nothing about that. The property that controls it is the g-value, the share of solar energy that passes through the glass.
For new homes, a separate regulation, Part O, deals with overheating, and it can limit the glazed area or require shading. Part O does not apply to extensions of existing homes, so a rear extension with a big rooflight over the kitchen has no regulation making sure it stays comfortable in July. That is the designer's job, and ours. Choosing a lower g-value on a south slope, adding external shading, or moving the rooflight so the sun falls on the floor rather than the worktop are all decisions that sit outside Part L.
The opposite case matters as well. On a north slope there is little direct sun to gain in winter, so the heat loss figure is almost the whole story, and a better-than-minimum U-value earns its keep. We look at that balance in do north facing rooflights lose more heat?, and at summer gain in rooflight overheating in summer.
Listed buildings and conservation areas
Historic buildings get some flexibility under Part L where meeting the letter of it would harm their character, but that flexibility is limited and has to be agreed rather than assumed.
Approved Document L recognises that listed buildings, buildings in conservation areas and other traditional buildings may need a different approach, where fitting modern elements would alter their character or cause moisture problems in older construction. The aim is still to improve energy performance as far as is reasonably practical without that harm. For a rooflight, this can come up where a slim steel conservation rooflight is the only type the planning side will accept, and the best available unit in that profile does not quite reach the figure a standard unit would.
In practice, modern conservation rooflights with sealed double glazing and thermal breaks reach 2.2 W/m²K in many sizes, so the question does not always arise. Where it does, the approach should be discussed with Building Control and, for a listed building, set out alongside the listed building consent. Cambridge and the surrounding districts have many conservation areas, from the city streets to village cores across South Cambridgeshire, so it is a common thread on local projects even when the answer turns out to be straightforward.
The key point for owners is that a heritage setting is a reason to talk to Building Control, not a reason to skip the notification. The record of what was agreed matters as much for an old cottage as for a new house.
Questions people ask
Does a roof lantern have to meet the same figure as a flat rooflight?
A roof lantern is assessed as a rooflight under Part L, so the 2.2 W/m²K limiting value applies to the lantern as a whole, including its glazing bars and ridge. Lanterns have a lot of frame for their glass area, so the whole-unit figure matters more than the glass alone.
Will a better rooflight improve my EPC?
It can, because rooflight U-values feed into the energy assessment, though a single small unit has a modest effect on the overall rating. The detail is in rooflights and EPC ratings.
Is the 2.2 W/m²K figure likely to change?
Standards for new homes are being tightened, and the Approved Documents are revised from time to time. Always check the edition in force when the work is notified. Specifying a rooflight comfortably better than the current minimum gives headroom whatever the next revision brings.
How do I know the rooflight I choose will comply?
Ask for the whole-unit U-value in the horizontal position for the exact size and glass. Every quote we give comes with a written light plan that sets out the unit, the glass and the reason for each choice, and our energy efficient rooflights service covers the specification from survey to the Building Control record. When you are ready, book a light survey.