How long each kind of lantern job takes on site
The time on site depends far more on what the roof needs before the lantern arrives than on the lantern itself. The glazed frame is the quick part; the opening, the kerb and the weathering around it set the pace.
A lantern skylight arrives as a kit: ridge, hips, rafters, glazing bars and sealed glass units, made to the measurements taken at the survey. Once the kerb is square, level and the right size, a two-person team can assemble the frame, bed the glass and fit the cappings in a working day on a typical kitchen extension lantern. Everything else on the timetable is preparation or finishing. The table below gives realistic ranges for the common situations around Cambridge, from a new build extension with a ready kerb to a retrofit on an older flat roof.
| Situation | Time on site |
|---|---|
| New extension, kerb built by the builder | About 1 day |
| Existing flat roof, new opening | 2 to 3 days |
| Replacing an older lantern on its kerb | 1 to 2 days |
| Wide span needing a steel frame | 3 days or more |
Those are working days on the roof. Plastering and decorating the light well inside run after the fitting and are covered further down.
The on-site sequence, day by day
On a retrofit into an existing roof, the work follows a fixed order, and each step has to be finished before the next can start.
- Day one, morning: access is set up, the room below is sheeted and the roof covering is cut back around the marked opening.
- Day one, afternoon: the joists are cut and trimmed to form the opening, and the upstand is built and insulated on the trimmers.
- End of day one: the roof covering is dressed up the upstand, or the opening is protected overnight if the covering has to wait.
- Day two: the lantern frame is assembled on the kerb, the glass units are bedded and clipped, and the cappings and ridge are fixed.
- Day two or three: the external trims are finished, the joint between covering and frame is checked, and the internal plasterboard lining of the upstand goes in.
On a new extension where the builder has already formed the opening and built the kerb, the first three steps are already done, which is why that job fits in a single visit. The roof lantern installation process guide explains what happens at each stage in more detail; this page is about the clock.
What stretches the timetable
Three things add days: the upstand and the structure under it, the weather, and the finishing inside. Knowing which of them applies to your roof is the best way to plan the week.
The upstand and the structure
A lantern sits on a timber kerb, usually around 150mm above the finished roof, so rain runs clear of the frame. Building it is quick on a sound roof. It takes longer if the joists run the wrong way for the opening, if they are undersized for the new load, or if the opening is wide enough that trimming alone will not carry it and a steel frame or beam is needed. A steel has to be designed, made and lifted in, and that is planned at survey stage rather than discovered on the day. The guide to the structural opening for a roof lantern covers those decisions, and the answer on how heavy a roof lantern is explains why a large triple-glazed unit needs more thought than a small one. Older roofs bring their own questions: whether the existing covering can be joined cleanly or needs renewing around the opening, and whether the deck is dry. Our answer on fitting a roof lantern to an existing flat roof goes through what a retrofit needs.
The weather
Nobody should leave a roof open in rain. If showers are forecast for the day the covering is cut, the start moves, or the opening is protected with a temporary cover and the weathering waits for a dry spell. Wind matters too: large glass units are lifted by hand onto the kerb, and a gusty day on an exposed roof on the edge of the Fens is not a day for it. Liquid and torch-on coverings also have temperature and moisture limits set by their makers, so a cold, damp week in November can add a day that a week in May would not.
Finishing inside
The light well, the short shaft of plasterboard between the ceiling and the base of the lantern, is boarded as part of the fitting. After that it needs skimming, drying and painting. Fresh plaster takes several days to dry before it can be decorated, longer in a cold room with the heating off. That work does not keep the roof open, but it does keep the room from feeling finished. How the well is shaped and lined also changes how far the light spreads, which is covered in how a roof lantern is finished inside.
The weeks before anyone arrives
Much of the elapsed time sits before the fitting: the survey, the light plan, the structural decisions and the manufacture of a made-to-measure frame.
At the survey we measure the roof, look at the structure, and work out where the light will land through the day and the year, which sets the size, position and glass. The written quote carries that light plan. Once the design is agreed, the lantern is made to order. Lead times vary by maker, frame material and colour, and a standard colour can be quicker than a special RAL finish or a dual-colour frame, so a lead time is confirmed with the quote rather than guessed. Choices made at this stage, such as aluminium or uPVC, solar control glass or an opening vent, can each affect how long the frame takes to arrive.
Paperwork runs in parallel. A lantern added to a new extension is usually covered by the extension's own approvals. Cutting a new opening in an existing roof changes the structure and the thermal performance of that roof, so it is normally notifiable under the Building Regulations; we handle the Building Control notification where the work is notifiable. In a conservation area or on a listed building, check the position with the planning authority before ordering. The planning rules for roof lanterns set out when permitted development applies.
What the days on site feel like at home
For a day or two the room under the opening is out of use, and the rest of the house carries on around it.
Expect noise while the roof is cut and the joists trimmed, some dust despite sheeting, and a ladder or tower outside. In a kitchen extension on a Romsey or Chesterton terrace, where the extension is the kitchen, it helps to clear the worktops and empty nearby cupboards before day one. Water and power usually stay on. Once the lantern is glazed, the room can be used again, with the light well to finish. The first sunny morning afterwards is when you see whether the light lands where the plan said it would, over the island or the table rather than across the hob.
To get a timetable for your own roof, book a light survey, and the written quote will set out the days on site, what is done before the fitting, and the glass and position for your orientation. The roof lantern installation page covers the wider service, and our costs guide explains what moves the price.
Questions people also ask
Can a roof lantern be fitted in one day?
Yes, when the kerb is already built, level and the right size, and the weather is dry. A replacement onto a sound existing kerb can also be a one or two day job. A new opening in an existing roof needs two to three days.
Does the roof stay open overnight?
It should not be left exposed. If the lantern cannot be glazed on the day the opening is cut, the upstand is weathered and the opening is closed with a temporary cover until the frame goes in.
How soon can I use the room again?
Usually as soon as the glass is in and the site is cleared. Plastering and painting the light well follow, and the room can be used while they dry.
Is the lantern skylight fitted before or after the rest of the extension?
On a new build it goes in once the roof deck, kerb and covering are done, before the internal plastering, so the well can be finished with the ceiling. Planning the order with your builder avoids a return visit.