Question

How long does sun tunnel installation take?

The short answer

As a general guide, a straightforward sun tunnel installation typically takes about half a day on site: one tube, a short straight run through an accessible loft, and a ceiling below with nothing awkward in the way. A long run, a second floor, several bends, a slate or flat roof detail, or an LED or ventilation kit can push it towards a full day. Two tubes in one visit can usually fit into a single day.

What a typical installation day involves

A sun tunnel is one of the quickest ways to bring daylight through a roof, because the roof opening is small and the ceiling hole is roughly the size of a dinner plate.

The time goes on a sequence of small, careful jobs rather than one big one. On a typical job with a pitched tiled roof over a loft, the day runs roughly like this:

  1. Setting out. The ceiling position is marked from below, then checked from the loft so the tube misses joists, cables and pipes. This is where the light plan from the survey becomes a real point on the ceiling.
  2. Cutting the ceiling. A neat circular hole is cut between the joists, with dust sheets down in the room below.
  3. Opening the roof. A few tiles are lifted, the membrane is cut, and the flashing collar is set into the roof so the tiles lap over it and water is shed around the dome.
  4. Running the tube. The reflective tube sections are joined from the roof down to the ceiling ring, with any angle adaptors needed to line up the two ends.
  5. Insulating and sealing. The tube is wrapped where it passes through the cold loft, and joints are taped so no warm, moist air gets in.
  6. Dome and diffuser. The dome goes on outside, the diffuser fits into the ceiling ring, and the room is cleaned down.

None of these steps is slow on its own. What decides whether the job finishes by lunchtime or runs into the afternoon is how easy each one is on your particular house. Our sun tunnel installation page covers the whole service, from the survey to the finished ceiling.

What stretches the time on site

The things that lengthen the job are almost all about the route the tube has to take and the roof it has to pass through.

The table below is a rough guide to how each factor tends to affect the day. None of it is fixed, and the survey is where your own timing gets worked out.

FactorTypical effect on the day
Short straight loft runAbout half a day
Long run or several bendsAn extra hour or two
Through an upper floorOften a full day
Slate or flat roof detailExtra time at roof level
LED or ventilation kitExtra time for wiring or ducting
Tight or boarded loftSlower access and routing

Length and bends matter for the light as well as the clock. Each extra section and angle adds joints to seal and takes something off the brightness at the diffuser, which is why a straight run is worth planning for. Our guide to sun tunnel length and bends explains the trade-off. A tube that drops through a bedroom cupboard to light a ground floor hall is a bigger job again, because it needs a boxed-in chase on the upper floor; our answer on whether a sun tunnel can go through two floors covers what that involves.

Extras add time in their own way. An LED light kit needs a supply run to it, and a ventilation kit in a bathroom needs its extract connected and its wiring completed. Product details vary between manufacturers and models, so the exact steps depend on the kit chosen.

How the roof covering changes the job

The roof covering decides how long the work at the top takes, and it is the part that has to be right for the whole life of the tube.

On concrete interlocking tiles, the flashing sits under the tiles above and over the tiles below, and the work is fairly quick. Plain clay tiles, found on many older Cambridge terraces and village cottages, are smaller, so more of them need lifting and refixing around the collar. Natural slate is slower again, because slates are fixed individually and have to be worked around the flashing by hand. Our answer on fitting a sun tunnel to a slate roof goes into the detail.

Flat roofs are a different job. The tube usually needs an upstand or kerb sealed into the roof covering, whether felt, single ply or GRP, so the dome stands clear of any standing water. The run below is often short, which saves time inside, but the roof detail takes care. Our guide to sun tunnels for flat roofs shows how the upstand is formed.

Weather, paperwork and the time before the day

The on-site work is short, but a few things around it can set the overall timetable, and it helps to know them early.

Roof work needs a dry, reasonably calm day, so a wet or windy forecast can move the date. Scaffolding is not usually needed for a sun tunnel on an ordinary two-storey house, though a tall or steep roof can call for access equipment, which adds a visit to put it up and take it down.

Planning permission is not normally needed for a sun tunnel on a house, because it usually falls within permitted development, but conservation areas, listed buildings and flats can change that. Our answer on planning permission for sun tunnels sets out when it applies, and our answer on sun tunnels and building regulations explains when the work is notifiable. Where it is, we handle the Building Control notification, so you do not need to arrange it yourself.

What to have ready on the day

A little preparation keeps the day to its expected length and saves time spent shifting belongings.

  • A clear path to the loft hatch and some clear floor in the room below the diffuser position.
  • Stored boxes moved away from the part of the loft where the tube will run.
  • Parking close enough for ladders and tube sections to be carried in.
  • Pets and children kept out of the room while the ceiling is open.

The dust from a sun tunnel is modest compared with a roof window or a lantern, but the ceiling cut does make some, so fragile or valuable items in that room are better moved beforehand.

Questions people also ask

Can I use the room the same day?

Yes. Once the diffuser is in and the room is cleaned down, the room is ready to use, and the tube starts passing daylight straight away. There is no drying or curing time to wait for on a typical pitched roof sun tunnel.

Do I need to be at home during the installation?

Someone should be there at the start to confirm the diffuser position in the room, and at the end to see the finished job. In between, the work is mostly in the loft and on the roof.

Does loft insulation add time?

Only a little. The insulation is moved aside for the tube and then put back around it, and the tube itself is wrapped. Our answer on whether a sun tunnel can go through loft insulation explains why this matters for condensation.

How do I find out how long mine will take?

A reliable answer comes from seeing the roof, the loft and the room. Book a light survey and your written quote will include a light plan with the position and size of the tube, along with the expected time on site.