Before anything is cut: setting out from the light plan
The first step in fitting a flat roof skylight happens with a tape measure and a pencil, not a saw. The position agreed in the written light plan is transferred onto the ceiling and the roof, and checked against the joists, the walls and the room below before a single board is lifted.
By the time the fitting day arrives, the big decisions are settled. The size, the glass, whether the unit opens, and exactly where it sits over the kitchen island or the dining table were all agreed at the survey and written into the quote. What the setting out does is prove that the agreed position still works once the ceiling is looked at closely. A joist can run a few centimetres from where the drawings said. A downlight circuit or an extractor duct can cross the line of the opening. A soil pipe can rise through the roof of a side-return extension closer to the rooflight than anyone expected.
So the fitter marks the four corners of the structural opening on the ceiling, then finds the same corners on the roof by measuring from fixed points: the rear wall, the party wall, the edge of the roof. The two sets of marks have to agree. If they do not, it is far better to find out now than with a hole already cut. At this stage we also check the distance to any party wall, because a rooflight should stay out of the 1500mm zone either side of it for fire-spread reasons, which is covered in more depth in our answer on how close a rooflight can be to a party wall.
A final look at the light is worth a minute here. Stand where the table or worktop will be and look up at the marks. On a south-facing plot in Trumpington or Great Kneighton, the midday sun patch from a flat rooflight lands a little north of the opening in summer and further north in winter, so a unit set right over the island throws its sun onto the island's far edge by February. That shift was allowed for when the position was planned, and the setting out simply confirms the numbers still hold. If you want the reasoning behind the position itself, our guide to positioning a flat roof skylight goes through it.
Protecting the room and opening the ceiling
Inside, the room is sheeted and sealed off before the ceiling is opened, because cutting plasterboard and lifting a roof deck makes dust that travels. Then the ceiling is cut back to the marked line, which exposes the joists and shows what the roof is really made of.
Floors are covered with protective sheet and boards, worktops and appliances are wrapped, and a dust screen is set up if the kitchen opens into the rest of the house. In a lived-in terrace on Mill Road or in Romsey, where the kitchen extension is often the route to the garden, we agree with you beforehand which door stays usable so the household can still get in and out.
The plasterboard is scored and cut along the line of the structural opening. Once it comes down, the roof build-up is visible for the first time from inside, and this is the moment to confirm what the survey found: the joist size and spacing, which way they span, whether there is insulation between them or above the deck, and whether there is a vapour control layer. A cold deck roof, with insulation between the joists and a ventilated gap above, needs different detailing at the upstand from a warm deck roof with the insulation on top of the deck. Our answer on whether a rooflight can be fitted to a warm deck flat roof explains that difference.
Any cables in the way are made safe and rerouted. Downlights near the edge of the opening are moved so they do not end up half in the reveal. None of this is dramatic, but doing it carefully now saves the finished ceiling from having lights crowded against the rooflight or a switch that no longer works.

Trimming the joists and forming the structural opening
With the ceiling open, the joists that cross the opening are cut back and their loads carried by new trimmers. This is the structural heart of the job, and it follows either a standard trimming detail or an engineer's specification, depending on the size of the opening and the roof.
Before any joist is cut, the roof is propped from below with adjustable props and a spreader, so nothing moves when the load path changes. The joists that will be cut are then marked, and the new timbers are fixed in first where possible. The usual arrangement is a pair of trimmer joists either side of the opening, doubled up alongside the existing joists, with trimming pieces across each end that pick up the cut joists on joist hangers. Everything is bolted or nailed to the pattern the design calls for.
For a modest opening that sits between the existing joists, or cuts only one or two of them, a standard detail can be enough. A larger opening, a long linear unit, or a roof that already carries a heavy covering or a green roof build-up may need an engineer to size the new members. The question of when that applies is dealt with properly in our answer on whether a flat roof needs strengthening for a rooflight. Either way, the calculation or the detail is part of the Building Control file for the job.
Only when the trimming is complete is the deck cut through from above, along the line of the new timbers. The opening is then checked for size and square by measuring the diagonals: equal diagonals mean a square opening, and a square opening means the upstand and the rooflight will sit true. On an existing roof we try to keep the time the deck is open to the sky as short as possible, which is why the kerb materials are cut and ready before the saw goes in.
Building the upstand and setting the fall
The upstand, or kerb, is the frame the rooflight sits on. It lifts the glass clear of standing water, gives the roof covering something to turn up against, and, on many flat roof skylights, provides the slope that lets rain run off the glass.
- Joists, with doubled trimmers either side of the opening to carry the loads of the cut joists around it.
- Deck (usually 18mm ply or OSB) with a vapour control layer laid on it.
- Insulation boards above the deck (a warm roof), often tapered to give the roof its falls.
- Waterproof membrane dressed up the upstand and over its top, so the joint is lapped, not sealed.
- Upstand, or kerb: insulated timber, finishing at least 150mm above the finished roof surface to keep standing water and splash off the joint.
- Rooflight unit fixed over the kerb, its frame skirt shedding water outside the membrane turn-up.
- Plastered reveal lining the opening from the ceiling up to the frame, finished white to bounce the light down.
- Roof falls to an outlet: designed at about 1:40 so the finished roof never falls less than 1:80.
A site-built timber upstand is formed from treated timber fixed to the trimmers, sized so that the top of the kerb finishes at least 150mm above the finished roof surface. That height is measured from the top of the finished covering, not from the deck, so the thickness of the insulation and membrane that will go on later is allowed for from the start. Some manufacturers supply an insulated factory upstand instead, which arrives square and ready to fix; the choice between the two is set out in our guide to flat rooflight upstands.
Flat rooflights need their glass laid to a fall, with around 5 degrees the widely quoted figure for water to clear. Where the rooflight itself is not made with a built-in pitch, the upstand is built with one side higher than the other to create it. The fall runs towards the roof's own drainage, so water leaving the glass heads for the gutter or outlet rather than across the roof towards a wall. The fitter checks the fall with a digital level before anything else goes on top. A kerb that is a degree short of its fall is easy to adjust at this stage and a nuisance to put right later.
There is a light consequence to the kerb, too. The taller and deeper the upstand and the inner reveal, the more the opening behaves like a short tube: it narrows the spread of sky the room can see. Splaying the internal lining, which comes later, is how that is recovered.
Insulating the kerb and carrying the vapour control layer
A timber kerb on its own is a cold bridge between the heated room and the outside air. So it is insulated on the outside and the vapour control layer from the roof is carried up and sealed to it, keeping the warm, moist air of the room away from cold surfaces inside the roof.
On a warm deck roof, the insulation boards that sit on the deck are cut tightly around the upstand, and a strip of insulation is fixed up the outer face of the kerb so the insulation line runs unbroken from roof to rooflight frame. On a cold deck roof the detail is different, and care is taken not to block the ventilation path above the insulation between the joists.
The vapour control layer is the less visible step and one that matters a great deal. It is lapped up the kerb and sealed, so there is no gap at the corners where moist air from a steamy kitchen could get into the roof void and condense on the cold side of the insulation. Corners are the weak point, and they are folded and taped rather than cut and hoped for. Our answer on whether a flat rooflight needs a vapour control layer explains why this layer earns its place.
Weathering the roof covering up the upstand
Next, the roof covering is dressed up the outside of the kerb and over its top edge, so that water on the roof meets a continuous waterproof surface rising above the drainage level. This is the step that keeps the roof dry for decades.
How it is done depends on the covering. An EPDM rubber roof is turned up with a separate upstand strip bonded to the main sheet with the manufacturer's tape and primer. A GRP fibreglass roof has a pre-formed angle fillet at the base of the kerb, then matting and resin laid up the face, with the topcoat applied over it. A single-ply membrane is heat-welded, and a torch-on felt roof is dressed up in layers with a fillet at the base. Where the existing covering is in poor shape, it is often more sensible to renew the area around the rooflight, or the whole roof, while the job is open. Our guide to flat rooflights and roof coverings explains each covering and who does which part, and lead and zinc roofs follow their own metalwork detail.
Weather matters at this step more than any other. Membrane adhesives and resins have temperature and moisture limits, so on a cold, damp morning in a Fenland January the weathering may wait until the deck is dry and the temperature has risen. A temporary cover keeps the opening watertight in the meantime.
Setting and fixing the rooflight
With the kerb weathered, the rooflight unit is lifted on, set square and level to the fall, bedded on its seals and mechanically fixed. On a larger unit this is a two or three person lift, planned in advance.
Framed units sit over the upstand with the frame's own skirt covering the top of the membrane, and are screwed through the frame into the kerb at the manufacturer's spacings. Frameless units, where the glass is bonded directly, are set on a bed of the specified sealant or gasket and fixed through their perimeter; the glass edge has to overhang the kerb evenly all round. The differences in how the two types weather are explained in our guide to framed vs frameless flat rooflights.
Heavier glazed units, particularly triple glazed or large single panes, are lifted with suction cups and set down onto spacers so the seals are not dragged. Once the unit is fixed, the fitter checks it again: square to the kerb, consistent overhang, and the fall still running the right way. An opening or electric unit is wired and tested at this stage, including any rain sensor, so it closes as it should before the ceiling is finished and the cables are hidden.
The roof side is now complete. From the garden the rooflight looks finished, and the room below is already brighter, even with sheeting still on the floor.
Lining the reveal and finishing the ceiling
The internal reveal is the short shaft between the ceiling and the underside of the rooflight. How it is lined decides how much of the light that comes through the glass actually reaches the room, and whether the finished ceiling looks crisp or pieced together.
The reveal is framed out in timber, then lined with insulated plasterboard so the cold bridge at the kerb is closed from inside as well. Where the light plan calls for it, the sides of the reveal are splayed outwards towards the room rather than left vertical. A splayed reveal lets the room see a wider spread of sky and softens the edge of the light on the ceiling, which reduces the hard contrast between the bright opening and the surrounding plaster. On a deep roof, a splay can make a noticeable difference to how bright the room feels on a grey day.
The ceiling around the opening is made good with new board where needed, then taped, skimmed and left to dry. Plaster beads on the corners keep the arrises straight. Once the skim is dry, the reveal is ready for decoration, and a pale, matt finish inside the reveal reflects the most light downwards. If the plan includes a blind, the fixing points and any wiring for it are allowed for before plastering, as explained in our answer on whether a flat rooflight can have an integral blind.
The checks at each stage, and handing over
A flat roof skylight is only as good as its least visible layer, so each stage has its own check before the next one covers it. The job is signed off only when the whole sequence has been checked, the room is clean and the paperwork is complete.
| Stage | What is checked |
|---|---|
| Setting out | Position matches the light plan; clear of the party wall zone |
| Trimming | Props in; trimmers sized; opening square |
| Upstand | 150mm above finished roof; fall to drainage |
| Insulation and VCL | Continuous line; corners sealed |
| Weathering | Covering bonded up and over the kerb |
| Unit | Square, fixed, seals seated; vents tested |
| Reveal | Insulated, splayed if planned, skimmed true |
The Building Control notification is handled for you where the work is notifiable, and a new rooflight in an existing roof normally involves Part A (structure), Part L (thermal performance) and, depending on its position, Part B (fire) and Part K (safety glazing overhead). At the end of the job you receive the completion paperwork, the manufacturer's product documentation and the details of our 10-year workmanship guarantee on the installation. The time the whole sequence takes, from a same-size replacement to a new opening, is set out in our answer on how long flat rooflight installation takes.
The last check is the one this whole page leads to. Once the sheeting is off, we look at where the light is falling. The patch of sky over the island, the wash along the back wall, the brightness in the far corner of a side-return: the finished room should match what the light plan described. The full service, from survey to handover, is on our flat roof rooflight installation page, and if you would like to see the light plan for your own room before anything is cut, book a light survey.
Questions people ask
Can a flat roof skylight be fitted without replacing the whole roof?
Yes, where the existing covering is sound. The new rooflight is weathered into the surrounding covering with a compatible material. If the covering is near the end of its life, renewing it at the same time is often the better plan, because the roof is already open and access is in place. Our answer on whether a flat rooflight can be fitted to an existing roof covers this in more detail.
Do I need to move out while the rooflight is fitted?
No. The room below is sheeted and screened, and the opening is kept watertight with a temporary cover whenever work stops. The kitchen or living space under the rooflight is out of use for part of the job, and we agree beforehand which rooms and doors you can still use.
What does the flat rooflight fitting sequence look like if I am replacing an older unit?
The steps are much the same, with the old unit removed first and the existing kerb inspected. If the kerb is sound, the correct height and square, it can take the new unit after the covering is renewed around it. If it is too low, rotten or out of square, it is rebuilt, and the new rooflight is fitted to it following the same stages described above.