What cutting an opening does to a flat roof
A flat roof is a row of parallel joists sharing the load of the deck, the covering, the insulation and any snow, so taking one out of the row moves its share onto its neighbours.
Timber flat roofs on Cambridge extensions are commonly built with joists at 400mm or 600mm centres, spanning from the house wall to the outer wall or a steel beam. A rooflight with a 1000mm by 1000mm structural opening is wider than any one of those gaps, so one or two joists have to stop short of it. The short lengths that remain are called trimmed joists, and they hang from a trimmer running across the opening. The trimmer in turn hangs from the trimming joists on each side, which now carry their own load plus half of everything the cut joists used to carry.
The rooflight adds weight of its own. Glass weighs about 2.5kg per square metre for every millimetre of thickness, so a double glazed unit with a laminated inner pane is roughly 30kg per square metre before the frame and kerb are counted, and triple glazing adds more. That load sits on the upstand, and the upstand sits on the trimmers. None of it is large compared with a whole roof, but it lands on exactly the members that have just lost help. The upstand guide explains how the kerb spreads that weight along the edges of the opening.
When trimming the existing joists is enough
If the joists are sound, deep enough for their span and only one or two need cutting, doubling the joists either side and fitting a doubled trimmer across the cut ends normally does the job.
That is the typical position for a single rooflight in a modern single-storey extension with a clear drawing trail, where the joists were sized to published span tables and there is some reserve left. The trimming joists are doubled by bolting or nailing a second joist of the same depth alongside, running the full span and bearing at both ends. The trimmer is doubled too, and the connections are made with proper joist hangers rather than skew nails. Setting the opening so its long side runs with the joists, not across them, keeps the number of cut joists down, which is often the difference between a simple job and an engineered one.
Even on straightforward roofs someone has to check the numbers. Timber sizes, grades and spans can be looked up for simple trimming, and Building Control will want to see that the doubled members work. Where the original extension drawings exist, they save a lot of guesswork, because they state the joist size, grade and spacing that was approved.
When an engineer specifies new members
A structural engineer is the right call once the opening, the roof or the loads move outside what simple trimming covers, and the calculation then sets what goes in.
- Three or more joists are cut, as with a large single rooflight or a long linear rooflight running across the joists.
- The span is long and the joists are already working hard, which can happen on older extensions built with shallow joists.
- The roof carries extra load: a green roof, a terrace nearby, solar panels or plant.
- More than one opening falls in the same run of joists, so a trimmer would bear on a member that is already trimming another opening.
- The deck is concrete, as on some post-war garages and flats, or the roof is framed in steel.
- The joists show rot, splits, old notches for pipes or earlier alterations nobody recorded.
What the engineer specifies depends on the case. It might be deeper trimming joists, a glulam or LVL engineered timber beam, a steel flitch plate bolted between two joists, or a small steel beam on padstones where it bears on masonry. On a concrete deck the question becomes how to form the hole without weakening the slab, and the answer can include cutting limits and new edge support. The fee is usually modest next to the cost of getting it wrong, and the calculation goes straight into the Building Control file. Where the roof needs planting margins as well, rooflights on green roofs covers the extra loads and drainage.
| Situation | Likely structure |
|---|---|
| Fits between joists | No cutting, noggins only |
| One or two joists cut | Doubled trimming and trimmer |
| Three or more cut | Engineer, often a new beam |
| Green roof or plant | Engineer check |
| Concrete or steel deck | Engineer design |
Building Control and the paperwork
Cutting joists is a structural alteration, so the work falls under Part A of the Building Regulations, and a new rooflight in an existing roof is normally notifiable in its own right.
We handle the Building Control notification where the work is notifiable, and the structural detail forms part of it: the trimming arrangement, any engineer's calculation and the member sizes. The inspector may want to see the opening once it is formed and before it is closed up with the upstand and linings. That is another reason to settle the structure before anything is ordered. The same notification covers the thermal side under Part L and, near a party wall, the fire-spread zone, which the answer on rooflights near a party wall explains.
How the joists shape where the light lands
The structure and the light plan pull on the same decision, because the position that suits the joists is not always the position that suits the room.
Say the best place for a skylight in a Romsey side return is hard against the kitchen worktop, so the morning sun patch falls across the prep area. If that spot puts the opening across the joists, the choice is between an engineered beam there, or a rotated or shifted opening that trims fewer joists and still lands the light where it is needed. A move of 200 or 300mm, or turning a rectangular unit through ninety degrees, can keep the light almost the same and make the structure far simpler. The guides on positioning a flat roof skylight and flat rooflight sizes show how much room for movement there is before the light suffers. Every written quote from us carries a light plan that sets out that trade, so the position is agreed with its structural cost in view.
Questions people also ask
Can a rooflight sit between existing joists without cutting any?
Yes, if the structural opening is narrower than the gap between joists. At 600mm centres a small rooflight or a sun tunnel can fit between two joists with only noggins added to frame the ends. At 400mm centres very few units fit, so at least one joist is usually cut.
Does an old flat roof need strengthening more than a new one?
Not automatically, but less is known about it. Older roofs can have shallower joists, longer spans, hidden rot or unrecorded alterations, so they are more likely to need an engineer's check. The answer on fitting a rooflight to an existing roof covers the covering and insulation side.
Does replacing an old rooflight need new structure?
Not if the new unit uses the same opening. A same-size replacement sits on the existing trimming, which only needs checking for condition. Making the opening bigger means new trimming, and it is treated like a new opening.
Who decides whether an engineer is needed?
The surveyor flags it from the joist size, span and direction and the opening you want, and Building Control can ask for calculations at any point. When in doubt, a calculation is the safer route. Book a light survey and the structure is checked alongside the light plan for your flat roof rooflight.