From first cut to a terrace you can use
A walk-on skylight is built in a fixed order, and the glass can only be ordered once the opening it sits in actually exists, so the programme has a gap in the middle that the site days do not show.
Each stage below is a general guide for a single domestic pane of ordinary size on a house in and around Cambridge. Larger panes, multiple panes on a steel frame, or a roof that turns out to need more structural work all lengthen the programme.
- Survey and light plan. The position, size and finish are fixed on paper, including where the pool of light will fall in the room below. See how we plan the light.
- Engineer's input. Where joists are cut or a steel is needed, the opening is designed before anyone lifts a tool.
- Forming the opening. Joists are trimmed, the bearing is built and the kerb or upstand is set level and square.
- Measuring the formed opening. The glass is sized to what was built, not to a drawing.
- Manufacture. The laminated unit is made to order. The site is kept weathertight meanwhile.
- Setting the glass. The unit is lifted in, bedded on its bearing and sealed.
- Bringing the terrace up to the glass. Waterproofing, drainage and the finished surface are completed around it.
- Finishing below. The reveal is lined, plastered and decorated in the room underneath.
How the days and weeks add up
The site work itself is short. The calendar time is set mostly by design sign-off and the factory, and both vary with the product and the project.
| Stage | Typical time | What decides it |
|---|---|---|
| Forming a new opening | 2 to 4 days | Structure and roof build-up |
| Glass manufacture | Several weeks | Product and maker |
| Setting the glass | 1 day | Weight and access |
| Terrace finish round it | 1 to 3 days | Surface chosen |
| Lining the room below | 1 to 2 days | Plaster drying |
Treat the manufacturing line with the most caution. Lead times differ between makers, between standard and special sizes, and between a plain clear unit and one with a slip-resistant frit, a privacy interlayer or heated glass. The only reliable figure is the one the manufacturer confirms when the order is placed, and that figure goes into your written programme. Where the opening is part of a new extension, the builder forms it with the rest of the roof and the rooflight arrives later to go straight onto a ready bearing, which is the quickest route of all. The detail of the opening itself is covered in the structural opening for walk-on glass.
Why the glass cannot be ordered on the first day
Walk-on glass has no tolerance to take up a wrong measurement, so it is sized to the opening once the opening is built.
A standard flat rooflight sits on an upstand with some play around its frame. A flush walk-on unit is different: it has to bear evenly on all four edges, with a small, consistent joint to the terrace finish on every side. If the kerb is out of square by more than a few millimetres, the joint shows it, and if the bearing is not level the laminated pane can be stressed at one corner. That is why the opening is formed first, checked with a level and measured across both diagonals, and only then ordered.
The weeks of manufacture are not wasted time on site. The opening is closed with a temporary weathertight cover, and the room underneath can usually be used, with a temporary ceiling lining if the joists are exposed. On a roof terrace in Romsey or Chesterton where the terrace is the only outside space, it helps to know this gap is coming so the summer is not planned around a finished terrace that is still waiting for its glass. The glass itself is heavy for its size, as how heavy a walk-on rooflight is explains, and that affects the next stage.
The day the glass goes in
Setting the unit is typically a single day, but the weight and the route to the roof decide how that day runs.
A laminated walk-on pane is thick glass in several layers, so even a modest unit may need a team, a vacuum lifter or, for larger or higher panes, a hoist or crane. On a terraced street with no side access, the route may be through the house or over the rear boundary, and that is planned at survey rather than found out on the morning. Where a crane or road space is needed, a permit or suspension may have to be arranged in advance, which adds lead time of its own.
Once lifted, the pane is set onto its bearing, packed to the correct level so its top finishes flush with or just proud of the surrounding surface, and sealed. The sealant manufacturer states a curing time, and the glass should be kept clear of foot traffic and furniture until that time has passed. For what the glass can carry after that, see walk-on rooflight load ratings.
Finishing the terrace and the room below
A rooflight is not finished when the glass is sealed: the terrace has to be brought up to it and the ceiling below has to be closed around it.
On a roof terrace, the waterproofing is dressed up to the kerb and the drainage around the glass is completed, which is explained in drainage around flush walk-on rooflights. Then the surface goes down: porcelain paving on pedestals is typically quicker to lay than a bonded or screeded finish, which needs drying time before it is walked on. Decking sits somewhere in between. On a new terrace, the finished surface is often laid by the main builder once the glass is in, so the end date depends partly on their programme.
Below, the reveal between the ceiling and the glass is lined, plastered and left to dry before decorating. Fresh plaster typically needs several days before paint, longer in cold, damp weather. If the work is notifiable, the Building Control inspection is arranged around these stages, and we handle that notification where it applies. See building regulations for walk-on rooflights for what is checked.
What can stretch the programme
Most delays come from the roof, the weather or a change of specification, rather than from the glass itself.
Opening up an older flat roof sometimes shows joists running a different way from the drawings, a deck that needs renewing, or a build-up too thin to take the new insulation. Rain stops waterproofing work, and sealants and liquid membranes have minimum application temperatures, so a wet week in November can push a terrace back where the same job in June would not be affected. Changing the finish, the size or the glazing after the order is placed restarts the manufacturing clock. Adding a second pane or a steel support frame brings the engineer back in. Retrofits have their own points to check, set out in whether a walk-on rooflight can be fitted to an existing flat roof, and the full picture of the service is on the walk-on rooflight installation page. To get a programme for your own roof, book a light survey.
Questions people also ask
Can I use the room below while a walk-on rooflight is installed?
For most of the programme, yes. The room needs to be cleared and sheeted on the days the opening is cut and the glass is set, and there will be dust while the reveal is formed. During the manufacturing wait, a temporary cover keeps the opening weathertight.
How soon can I walk on the glass after it is fitted?
Only once the sealant has cured to the manufacturer's stated time and the terrace finish around it is complete. Until then, keep foot traffic, planters and furniture off it. The installer will tell you when it is ready.
Does replacing an existing walk-on unit take as long?
Typically less, because the opening already exists. The old pane is measured, the new one is made, and the swap itself is often a day, provided the bearing is sound and level. If the kerb needs rebuilding, allow extra days.
Does a walk-on skylight need planning permission, and does that add time?
Often it does not, but a terrace or a listed building can change that, and a planning application adds weeks before any work starts. See whether a walk-on rooflight needs planning permission.