Three kinds of job, three timetables
The glazed unit itself goes on quickly. What sets the length of the job is how much of the roof has to be made ready for it, so the first question is which of three situations you are in.
A new single-storey extension is the fastest case, because the builder frames the opening and builds the kerb while the roof is being formed. A retrofit into a roof that has been in place for years is the longest, because the opening, the structure and the covering all have to be reworked around the new glass. A replacement sits between the two: the opening is already there, but the old unit has to come off cleanly and the kerb has to be checked before anything new goes down onto it.
| Job | Days on the roof | Inside finishing |
|---|---|---|
| New extension, kerb ready | Half to 1 day | Often by the builder |
| New opening, existing roof | 2 to 3 days | A further visit |
| Replacement, sound kerb | 1 day | Light making good |
| Replacement, kerb rebuilt | 2 days | A further visit |
These are working days in dry weather. The weeks before the fitting, while a made-to-measure unit is manufactured, are a separate part of the programme and are covered below.
A new opening in an existing flat roof, day by day
This is the longest of the three: a rear kitchen or side-return roof that was built dark and now needs daylight through it.
Day one starts inside. The room below is cleared and sheeted, and the opening is marked on the ceiling at the position agreed in the light plan, so the sun patch falls on the worktop or table rather than on the floor by the door. Up on the roof the covering is cut back, the deck is opened and the joists are cut. Trimmers are fixed either side so the load of the cut joists is carried round the hole. If the roof needs more than simple trimming, that has been settled at survey; the answer on whether a flat roof needs strengthening explains when an engineer is involved.
Later on day one, the timber upstand is built on the trimmers and insulated, tall enough to stand at least 150mm above the finished roof. The vapour control layer is turned up inside it. Before the team leaves, the opening is closed and weathered for the night, either with the covering already dressed up the kerb or with a temporary cover.
Day two is the weathering and the glass. The EPDM, GRP, single-ply or felt covering is taken up the upstand and finished at the top edge, then the rooflight is lifted into place, bedded and fixed. A framed unit is screwed down through its fixing points; a frameless unit is set down onto its seals. The joint between covering and unit is checked all the way round.
Day three, where needed, is for the inside of the upstand: plasterboard lining to the reveal, corner beads and a skim. On a smaller roof with an easy covering, day two and day three often merge into one.
A replacement flat rooflight, day by day
Replacing a tired or misted flat skylight is usually quicker, because the opening, the trimming and most of the upstand already exist.
The morning is spent taking the old unit off. Its fixings are cut or unscrewed, the old sealant and trims are removed and the kerb is exposed. This is the moment that decides the timetable: a dry, square kerb of the right height lets the new unit go straight on, and the job is finished by the afternoon with new weathering at the top of the upstand.
If the old kerb is soft, too low or out of square, it is rebuilt before the new unit goes down. That adds a day, and it usually means the covering around it is renewed at the same time. A replacement is also the chance to improve the glass for the room: a south-facing unit that turned a kitchen into an oven can be renewed with solar control glass, which the flat rooflight glazing guide covers.
The weeks before and after the fitting days
The days on the roof are the short part. The whole programme, from light survey to painted reveal, is measured in weeks.
- Survey and light plan: the orientation, room use and roof build-up are checked, and the size, position and glass are agreed in writing.
- Manufacture: flat rooflights are generally made to order, and lead times for made-to-measure units typically run to a few weeks, varying by maker and season. Standard sizes can arrive sooner.
- Building Control: where the work is notifiable we handle the notification, and it runs alongside manufacture rather than adding time on the roof.
- Drying and decorating: fresh skim inside the upstand needs several days to dry before it takes paint well.
What can push the days out
Rain is the main cause of delay, because the covering cannot be dressed up the upstand on a wet deck.
Cambridge is one of the drier parts of the country, but a wet spell still holds the weathering back, and the adhesives and liquid coatings used with some coverings need a minimum temperature to cure. The answer on fitting a flat rooflight in winter goes into that. Other things that add time are access (a mid-terrace roof in Romsey or off Mill Road with no side passage means materials come through the house), a covering in poor condition that has to be renewed around the opening, a warm deck roof where the insulation has to be cut and closed carefully around the kerb, and a very large unit that needs lifting equipment. All of these are identified at the survey and written into the programme, so they are known before the roof is opened.
Questions people also ask
Can I stay in the house while a flat rooflight is fitted?
Yes. The work is on the roof and in one room below. That room is out of use while the opening is cut, and the rest of the house carries on as normal, though there will be some noise and dust sheeting on the first day.
Is the roof left open overnight?
No. Whatever stage the job has reached, the opening is closed and weathered at the end of each day, either with the unit in place or with a temporary cover.
Does fitting two or three rooflights take much longer?
Each extra opening adds time, but not a full job each, because access, protection and the covering work are shared. The guide to planning multiple flat rooflights covers spacing, and the flat roof rooflight installation page sets out the full service.
When will I know my own timetable?
After the survey. Your written quote and light plan give the days on site and the lead time for your unit. To get yours, book a light survey or message us on WhatsApp.